Scoring vendors without the black box

A vendor score is only as honest as its clock. Scored against first promises, May’s three main vendors separate clearly, and the twelve blocked invoices behind one of them stop hiding inside a weighted average.

RuleScore vendors from the landed documents: deliveries against first promise, blocks against invoices, and publish the arithmetic so purchasing argues inputs, not weightings.
Nevermeasure on-time against the last confirmed date. Every reschedule the vendor requests resets the clock, and chronic lateness grades itself out of the metric.
Three vendors scored from their own documents First promise, not last the clock that cannot reset Blocks joined in the quality half
A vendor score is only as honest as its clock. The first promise is the one the vendor cannot renegotiate afterwards.
◆ May scores, computeddeliveries, punctuality, blocks.
VendorReceiptsOn first promiseOn-time %Blocked invoices
Vendor A524892.33
Vendor B383181.612
Vendor C, intercompany292793.12
Smaller vendors231

Receipt counts are the vendor cut’s own rows, and the block column partitions the eighteen blocked invoices by who caused them. Vendor B’s twelve blocks against 38 deliveries is the finding the summary score would have smoothed away. Sample values are illustrative, never client data.

◆ The metric that forgives latenessthe reschedule loophole.

In common configurations, delivery punctuality is measured against the latest confirmed date, and practitioners report vendors managing the metric by reconfirming: ask to slip, get a new date, arrive on time. Scoring against the first promise closes the loophole and changes several rankings overnight.

◆ The black box retiredweights argued once, in the open.

The delivered evaluation blends criteria through configured weightings most buyers cannot see, so every review meeting relitigates the formula. Published arithmetic over landed documents moves the argument to the inputs, where it belongs.

Use case
Problem
Vendor scores come from a weighted black box, reschedules erase lateness, and the vendor causing a third of invoice blocks still scores well.
What we build
Scores computed in the open from landed receipts and blocks, on-time against first promise, every number traceable to its documents.
What you get
Vendor reviews with teeth: punctuality that cannot be renegotiated, quality joined from the invoice side, and rankings purchasing actually believes.
Would your vendor rankings survive a first-promise clock?
We rebuild the score from the documents and find out.
Talk to us
Terms on this page
SAP
The vendor. Systems, Applications, and Products in data processing.
HANA
SAP’s in-memory database, the platform S/4 runs on.
MM
Materials Management, the purchasing and inventory module.
ME65
The delivered vendor evaluation with its configured weightings.
first promise
The original confirmed delivery date, before reschedules.
reconfirmation
A vendor-requested new date; resets naive on-time clocks.
blocked invoice
An invoice the three-way match refused; see the blocks page.